Sunday, 26 October 2014

GIS INSTALLATION PROCEDURE

                 GIS INSTALLATION PROCEDURE
Ø  CHECK THE FLOOR LEVEL AND I BEAMS ARE IN PROPER LEVEL IF SO DO LEVEL CORRECTIONS BY GRINDING OR USING METAL SHIMS

Ø  CHECK THE LOADING CAPACITY OF OFFLOADING PLATFORM IN FRONT OF THE GIS ROOM. IT SHOULD BE CAPABLE OF CARRYING THE LOAD OF THE HEAVIER GIS PARTS AND SHOULD HAVE AN EXCESS MARGIN OF 1.5 TONS.

Ø  ENSURE THAT ROOM IS DUST PROOF AND CLEAN

Ø  ENSURE THAT OPENINGS PROVIDED ARE AS PER APPROVED DRAWING AND CHECK ONCE AGAIN AFTER INSTALLING BAYS EITHER IT WAS MATCHING TO BAY OR NOT

Ø  ENSURE THAT NO OTHER THEN RELATED TO GIS INSTALLATION PERSON IS ALLOWED TO WORK AREA

Ø  STICK GIS GA DRAWINGS ON THE WALLS FOR EASY REFERENCE

Ø  ENERGIZE THE HIGH BEAM LIGHTING CIRCUITS IN THE GIS ROOM

Ø  ENSURE THAT THE LOAD TESTING OF EOT CRANE IS COMPLETED PRIOR TO THE SHIFTING OF GIS BAYS

Ø  PLAN THE SHIFTING OF GIS TO SITE AFTER IDENTIFYING SUITABLE LOCATIONS IN FRONT OF GIS ROOM FOR STORAGE OF GIS BAYS, ACCESSORIES AND THE PARKING OF OFFLOADING CRANE AND TRAILERS.

Ø  FIRST CHECK THE GIS BELONGS TO YOUR SITE AND AFTER OPENING THE PACKINGS CHECK THE SI NOS MATCHING WITH FAT REPORT

Ø  CONFIRM WEATHER THE GIS BAYS WERE SINGLE OR DOUBLE COMPARTMENT

Ø  SHIFT THE BAYS TO INSIDE AND PLACE IN PROPER POSITION AS PER EQUIPMENT LATOUT

Ø  AFTER PLACING IT IN PROPER POSITION START THE PROCEDURE OF COMPARTMENT COUPLING

Ø  CHECK THE TOTAL MATERIALS ARRIVED AS PER THE PACKING LIST AND CHECK FOR THE TOOLS AND THE EQUIPMENTS TO BE SUPPLIED BY THE MANUFACTURER AND THE INSTALLATION CONTRACTOR
.
Ø  AFTER REMOVING THE COMPARTMENT JOINT CAP OF BOTH BAYS CLEAN THE 
CHAMBER THOROUGHLY WITH VACCUME CLEANER AND APPLY THE WHITE GREESE TO GAS CUT(INDUSTRIAL TYPE)

Ø  CHECK THE MALE AND FEMALE CONTACTS WERE SPACED AT EQUAL DISTANCE IF NOT FAULTY CONTACT TO BE CHANGED

Ø  THEN SLOWLY CLOSE THE BOTH THE BAY COMPARTMENTS BY GETTING IT TOGETHER REMOVE THE POLYTHENE COVER (TEMPORARILY CLOSED TO AVOID DUST ENTRY) AND START FIXING OF BOLT AND NUT TO COUPLING.
Ø  IN SAME WAY COMPLETE THE TOTAL BUS

Ø  AFTER COMPLETING THE COMPARTMENT COUPLING WE CAN START THE FOLLOWING PARALLEL WORKS

1.       DENSITY METER FIXING
2.       VACCUMING AND GAS FILLING
3.       VT INSTALLATION IS SAME AS COMPART MENT JOINTING
4.       PLATFORM ARRANGEMENT
5.       WELDING TO I BEAM
Ø  BEFORE VACCUMING FOR BUS BAR AND CABLE SEAL END WE HAD TO COMPLETE THE FOLLOWING WORKS
PD SENSOR TO BE INSTALLED
FEMALE CONNECTOR FOR CABLE SEAL END TO BE FIXED
      VACCUM AND GAS FILLING
IDENTIFY THE BAY AND CHAMBER FOR WHICH VACCUM TO BE DONE
OPEN THE CAP OF THE CHAMBER TO BE VACCUM CLEAN IT AND SILICA GEL TO BE REMOVED CLOSE THE CHAMBER PLATE
CONNECT  THE HOSE TO THE GD VALVE  TO VACCUM PUMP AND ENSURE THAT DENSITY METERS AND WERE INSTALLED PRIOR VACCUMING.
CONNECT THE PIRANI GUAGE SENSOR TO VACCUM PUMP
NOTE THE START TIME AND RECORD THE VALUES FREQUENTLY TIME AND VACCUM PRESSURE AND TIL IT REACHES 0.2TORR
IN BELOW PIC
GATE VALVE-1-  --------------- SF6 GAS HOSE CONNECTED TO VALVE
GATE VALVE-2------------------  PUMP VALVE
GATE VALVE -3 ---------------- USED TO CONNECT PIRANI GUAGE VACCUM SENSOR
GATE VALVE-4 ----------------- CONNECTED FOR CHAMBER HOSE
FOR VACCUMING THE VALVES POSITION TO BE AS BELOW
VALVE-2 ---------------- OPEN
VALVE-3 ----------------CLOSED
VALVE-1---------------- CLOSED
VALVE-4 ---------------OPEN
FOR MEASURING VACCUM PRESSURE VALVE POSITION TO BE AS FOLLOWS
VALVE-2 ---------------- CLOSED
VALVE-3 ----------------OPEN
VALVE-1---------------- CLOSED
VALVE-4 ---------------OPEN


FOR FILLING SF6 GAS  VALVE POSITION TO BE AS FOLLOWS
VALVE-2 ---------------- CLOSED
VALVE-3 ----------------CLOSED
VALVE-1---------------- OPEN
VALVE-4 ---------------OPEN
WHILE FILLING THE GAS WE HAVE TO OBSERVE THE DENSITY METER FOR GAS PRESSURE
SI NO
ACTIVITY
NO OF DAYS REQD
MANPOWER RE

1
BAY INSTALLATION AND ALIGNMENT WITH COMPARTMENT COUPLING
4 DAYS FOR 9 BAYS
15 ( FOR SHIFTING TIME) AND FOR ALIGNMENT WORKS 10 PEOPLE IS USED


2
VACCUM AND GAS FILLING
1 DAY 1 BAYS
2

3
VT INSTALLATION
2VTS PER DAY
6

4
PLATFORM ARRANGEMENT
4 DAYS
10

5
LCC PANELS
4 DAYS
10







LCC PANELS INSTALATION
Ø  ENSURE THAT BEFORE STARTING OF PANEL ERECTION EOT CRANE IS FREE
Ø  CHECK THE OPENING SIZES AND HORIZONTAL CLEARENCES WERE AVAILABLE FOR LCC PANELS FIXING
Ø  MARK ON THE FLOOR/WALL PANEL LOCATION AND CROSS CHECK THAT LCC PANEL SHOULD BE EXACTLY INFRONT OF CORRESPONDING BAY
Ø  MARK THE LOCATION OF FOUNDATION BOLTS AND START DRILL N FIX THE PANELS



NECESSARY MATERIALS TO CHECK BEFORE STARTING OF GIS WORKS
MAN POWER AND MATERIALS
1.       PACKING LIST
2.       SKILLED MAN POWER
3.       AUTHORISED RIGGER FOR EOT CRANE OPERATION
4.       CHAIN BLOCKS
5.       TOOL KIT
6.       LEVEL BLOCK
7.       LIFTING BELTS
8.       VACCUM MACHINE
9.       WATER BOTTLE WITH SPRAY ARRANGEMENT
10.   INDUSTRIAL TISSUE PAPERS
11.   2.5T PALLET TROLLEYS
12.   10T JACKS FOR LIFTING AND PLACING OF GIS BAYS
13.   WOODEN RACKS IN GIS ROOM FOR STORING MATERIALS
14.   STEEL CABINET WITH LOCKS
15.   WIDE TABLE -1 no.
16.   SMALL TABLE – 1no.
17.   CHAIRS – 4nos.
18.   32A AND 16A POWER SUPPLY OUTLETS
19.   AVAILABLITY OF VACCUM PUMP WITH BYPASS VALVE OR DELO MACHINE
20.   PIRANI GUAGE
21.   DEW POINT METER
22.   GAS LEAKAGE METER
23.   19MM HOSE FOR VACCUM AND GAS FILLING